By Joseph muyingo
KAMPALA
FBW Faces 45-Day Deadline After Court Orders Security in Meera Investments Dispute Group has been given 45 days to secure USD132,750 if it is to prevent Meera Investments from moving ahead with enforcement of a disputed USD741,250 judgment.
The court’s decision offers FBW temporary relief from immediate execution, but the stay comes with a financial condition that places the company under a strict deadline as it pursues its intended appeal.
The USD132,750 represents the principal amount Meera Investments paid for disputed construction milestones and is regarded as the undisputed portion of the judgment.
However, much of the larger award remains contested.
FBW is challenging the additional USD108,500 in special damages and USD500,000 in general damages, meaning the parties remain divided over a substantial portion of the judgment.
The court consequently declined to require FBW to provide security for the entire USD741,250, instead limiting the immediate security requirement to the USD132,750 principal amount.
The ruling effectively gives FBW breathing space to pursue its appeal while protecting the portion of the judgment that the court considers undisputed.
The 45-day period now becomes critical.
If FBW secures the required USD132,750 within the stipulated period, execution of the judgment will remain stayed as the appeal process proceeds.
Failure to meet the condition, however, would open the door for Meera Investments to pursue execution of the full judgment amount, together with applicable interest and costs.
The decision therefore creates a delicate balance between the two sides.
For FBW, the ruling provides an opportunity to challenge the contested damages without facing immediate enforcement, but it also imposes a significant financial obligation within a limited timeframe.
For Meera Investments, the ruling preserves a pathway to recover the judgment if FBW does not comply with the court’s condition.
The costs associated with the stay application will also be determined by the outcome of the intended appeal.
The dispute therefore moves into a new phase, with the focus shifting from immediate execution to whether FBW can satisfy the court’s security requirement while pursuing its challenge to the contested damages.
The case underscores the financial consequences that can arise from prolonged commercial and construction disputes, where disputed claims can continue to carry significant monetary exposure even as parties pursue further legal remedies.